Schedule Details (rev 02-04-04) |
||
|
There are two groups listed below. Group A or [A] and Group B or [B]. Group [A] has selected their primary launch to be April 17, 2004. Group [B] has selected their launch to be August 7, 2004.
|
||
| Schedule Item | Due Date | Status |
| Program Start | 02-04-04 | Complete |
| Mission Selection (Top Three) & Launch Date Selection | 02-18-04 | Complete |
| Final Mission Selection and Student Teams Finalized | 03-03-04 | Complete |
| [A] Slides for Launch Readiness Review (LRR) due via email by 4:00 PM | 04-01-04 | Complete |
| [B] Slides for Critical Design Review (CDR) due via email by 4:00 PM | 04-01-04 | Complete |
| [A] LRR in Boulder from 1:00 - 7:00 PM | 04-02-04 | Complete |
| [B] CDR in Boulder from 1:00 - 7:00 PM | 04-02-04 | Complete |
| Undergraduate Research Symposium in Boulder from 9:00 AM to 3:00 PM, all students encouraged to attend | 04-03-04 | Complete |
| [A] Launch in Windsor, Colorado at 7:00 AM, must be at launch site by 5:45 AM | 04-17-04 | Complete |
| [B] On-site visits held during month of July and complete by July 30, 2004 | 07-30-04 | |
| [B] Slides for Launch Readiness Review (LRR) due via email by 4:00 PM | 08-05-04 | |
| [A] Slides for Final Report Presentation due via email by 4:00 PM | 08-05-04 | |
| [B] LRR in Boulder from 1:00 - 7:00 PM | 08-06-04 | |
| [A] Final Report Presentations in Boulder from 1:00 - 7:00 PM | 08-06-04 | |
| [B] Launch in Deer Trail, Colorado at 7:00 AM, must be at launch site by 5:45 AM | 08-07-04 | |
| Final Reports from all schools due | 11-01-04 | |
|
|
||
|
|
||
|
|